Readiness Days of Guaranteed Capacity Sources

01-23/09/2018
Ready
Not Ready

 Readiness Days (Forecast) of Guaranteed Capacity Sources

September, 2018

GUARANTEED CAPACITY SOURCES

Planned Readiness Days

Actual Readiness Days
01-23

"G-power" LTD Air Turbine TPP 30 Day 23 Day
"Georgian International Energy Corporation" LTD Energy Unit N:3 Gardabani TPP 30 Day 23 Day
"Georgian International Energy Corporation" LTD Energy Unit N:4 Gardabani TPP 30 Day 23 Day
"Mtkvari Energy" LTD Energy Unit N:9 Gardabani TPP 20 Day 11 Day
"Gardabani Thermal Plant" LTD Combined TPP 30 Day 23 Day
  • After the completion of planned maintenance, the Energy Unit №9 owned by the Ltd “Mtkvari Energy” was tested due to the request of the capacity source, on September 11-12, 2018, to check the readiness of guaranteed capacity, which was successful.
    Thus, the Energy Unit №9 owned by the Ltd “Mtkvari Energy” is ready to provide for the guaranteed capacity since September 13.