Readiness Days of Guaranteed Capacity Sources

01-19/07/2018
Ready
Not Ready

 Readiness Days (Forecast) of Guaranteed Capacity Sources

July, 2018

GUARANTEED CAPACITY SOURCES

Planned Readiness Days

Actual Readiness Days
01-19

"G-power" LTD Air Turbine TPP 31 Day 19 Day
"Georgian International Energy Corporation" LTD Energy Unit N:3 Gardabani TPP 31 Day 19 Day
"Georgian International Energy Corporation" LTD Energy Unit N:4 Gardabani TPP 0 Day 0 Day
"Mtkvari Energy" LTD Energy Unit N:9 Gardabani TPP 4 Day 4 Day
"Gardabani Thermal Plant" LTD Combined TPP 23 Day 9 Day
  • The planned repair of the Ltd "Gardabani Thermal Power Plant" will be completed on July 8, 2018 instead of June 30, 2018. Therefore, the Ltd "Gardabani Thermal Power Plant" was not ready to insure the Guaranteed Capacity starting from July 1 till July 8 (including), for 8 day.
  • On July 9-10, 2018, the Ltd "Gardabani Thermal Power Plant" was tested to check the readiness for provision of guaranteed capacity, which was successful. Thus, the Ltd "Gardabani Thermal Power Plant" is ready to provide for the Guaranteed Capacity from 11 July.

NEXT MONTH READINESS DAYS (FORECAST) OF GUARANTEED CAPACITY SOURCES