The Guaranteed Capacity buyer Eligible Enterprise (Distribution Licensee, Direct Customer and Exporter) is obliged to compensate the Electricity Market Operator the cost of Guaranteed Capacity (by each Source of Guaranteed Capacity), payable to the Guaranteed Capacity sources during the corresponding settlement period. The payment should be in proportion with the actual consumption of Guaranteed Capacity buyer enterprise in total consumption and export or in proportion with the export share.

Distribution licensee

Direct Customer

Exporter

Note: An exporter pays for the cost of the Guaranteed Capacity in the event that the export actually took place.

 

Guaranteed Capacity Buyer Qualified Enterprises Actually Consumption and Guaranteed Capacity Cost, 2017

PERIOD

Qualified Enterprises
Consumption (kWh)

Guaranteed Capacity
Cost (GEL)

January 834 268 262 14 774 570
February 778 322 170 13 636 170
March 813 756 126 15 135 967
April 761 594 703 14 647 710
May 923 633 645 14 339 528
June 998 387 016   3 875 852
July 1 093 440 014 11 046 315
August 949 182 501 12 678 303
September 816 737 167 12 942 126
October 810 306 344 15 135 967