The Guaranteed Capacity buyer Eligible Enterprise (Distribution Licensee, Direct Customer and Exporter) is obliged to compensate the Electricity Market Operator the cost of Guaranteed Capacity (by each Source of Guaranteed Capacity), payable to the Guaranteed Capacity sources during the corresponding settlement period. The payment should be in proportion with the actual consumption of Guaranteed Capacity buyer enterprise in total consumption and export or in proportion with the export share.

Distribution licensee

Direct Customer

Exporter

Note: An exporter pays for the cost of the Guaranteed Capacity in the event that the export actually took place.

 

Guaranteed Capacity Buyer Qualified Enterprises Actually Consumption and Guaranteed Capacity Cost, 2018

PERIOD

Qualified Enterprises
Consumption (kWh)

Guaranteed Capacity
Cost (GEL)

January 920 654 413 16 366 247
February 842 356 827 14 258 165
March 906 863 691 16 411 121
April 892 278 382 15 881 730
May 1 060 199 104 9 120 598
June 1 072 987 992 3 913 563