Readiness Days of Guaranteed Capacity Sources

01-14/07/2024
Ready
Not Ready

 Readiness Days (Forecast) of Guaranteed Capacity Sources

July, 2024

GUARANTEED CAPACITY SOURCES

Planned Readiness Days

Actual Readiness Days
01-14

"G-power" LTD Air Turbine TPP 31 Day 14 Day
"Georgian International Energy Corporation" LTD Energy Unit N:3 Gardabani TPP 27 Day 12 Day
"Georgian International Energy Corporation" LTD Energy Unit N:4 Gardabani TPP 0 Day 0 Day
"Mtkvari Energy" LTD Energy Unit N:9 Gardabani TPP 0 Day 0 Day
"Gardabani Thermal Plant" LTD Combined TPP 7 Day 7 Day

Additional Information about the Readiness of Guaranteed Capacity Source:

  • On October 11 and 12, 2022, at the request of the dispatcher, The Ltd “Gardabani Thermal Power Plant” successfully passed the test of readiness to provide guaranteed capacity.

    On October 11, at 09:00, the plant synchronized, reached, and maintained the minimum guaranteed capacity (162 MW) established by the state within the time limits stipulated by the current legislation. The plant worked in a test mode until 19:30 on October 12, after which it remained in service by order of the dispatcher.

NEXT MONTH READINESS DAYS (FORECAST) OF GUARANTEED CAPACITY SOURCES