Readiness Days of Guaranteed Capacity Sources

01-15/06/2021
Ready
Not Ready

 Readiness Days (Forecast) of Guaranteed Capacity Sources

June, 2021

GUARANTEED CAPACITY SOURCES

Planned Readiness Days

Actual Readiness Days
01-15

"G-power" LTD Air Turbine TPP 31 Day 15 Day
"Georgian International Energy Corporation" LTD Energy Unit N:3 Gardabani TPP 31 Day 15 Day
"Georgian International Energy Corporation" LTD Energy Unit N:4 Gardabani TPP 14 Day 0 Day
"Mtkvari Energy" LTD Energy Unit N:9 Gardabani TPP 31 Day 15 Day
"Gardabani Thermal Plant" LTD Combined TPP 31 Day 0 Day

Additional Information about the Readiness of Guaranteed Capacity Source:

  • We would like to inform you that on March 4 and 5, 2021, at the request of the Dispatcher, the 9th power unit owned by the Ltd “Mtkvari Energy” was tested for the readiness to provide guaranteed capacity, which was successful. Thus, the 9th power unit owned by the Ltd “Mtkvari Energy” has the necessary readiness to provide guaranteed capacity in March 2021.

NEXT MONTH READINESS DAYS (FORECAST) OF GUARANTEED CAPACITY SOURCES