Readiness Days of Guaranteed Capacity Sources

01-12/11/2019
Ready
Not Ready

 Readiness Days (Forecast) of Guaranteed Capacity Sources

November, 2019

GUARANTEED CAPACITY SOURCES

Planned Readiness Days

Actual Readiness Days
01-12

"G-power" LTD Air Turbine TPP 30 Day 12 Day
"Georgian International Energy Corporation" LTD Energy Unit N:3 Gardabani TPP 30 Day 12 Day
"Georgian International Energy Corporation" LTD Energy Unit N:4 Gardabani TPP 30 Day 12 Day
"Mtkvari Energy" LTD Energy Unit N:9 Gardabani TPP 30 Day 12 Day
"Gardabani Thermal Plant" LTD Combined TPP 30 Day 12 Day

Additional Information about the Readiness of Guaranteed Capacity Source:

  • On November 1 and 2, 2019, at the dispatcher’s request, the 9th power unit owned by Mtkvari Energy Ltd was tested to verify the availability of guaranteed capacity. Testing was successful. Thus, the 9th power unit owned by Mtkvari Energy Ltd is ready to provide guaranteed capacity in November 2019.

NEXT MONTH READINESS DAYS (FORECAST) OF GUARANTEED CAPACITY SOURCES