Readiness Days of Guaranteed Capacity Sources

01-29/10/2020
Ready
Not Ready

 Readiness Days (Forecast) of Guaranteed Capacity Sources

October, 2020

GUARANTEED CAPACITY SOURCES

Planned Readiness Days

Actual Readiness Days
01-29

"G-power" LTD Air Turbine TPP 31 Day 29 Day
"Georgian International Energy Corporation" LTD Energy Unit N:3 Gardabani TPP 31 Day 29 Day
"Georgian International Energy Corporation" LTD Energy Unit N:4 Gardabani TPP 31 Day 29 Day
"Mtkvari Energy" LTD Energy Unit N:9 Gardabani TPP 31 Day 29 Day
"Gardabani Thermal Plant" LTD Combined TPP 31 Day 29 Day

Additional Information about the Readiness of Guaranteed Capacity Source:

  • We would like to inform you that on September 21, 2020, at the request of the capacity source, the 4th power unit belonging to the Georgian International Energy Corporation, Ltd passed test for readiness to provide guaranteed capacity, which was successful. The order to launch the power unit was issued on September 21 at 01:00, synchronization was performed at 05:24, the power unit failed and retained the minimum guaranteed capacity (100 MW) established by the state within the timeframes stipulated by the current legislation, then (at 23:00 on September 21st) was stopped in reserve by order of the Dispatcher. Thus, the 4th power unit belonging to the Georgian International Energy Corporation, Ltd has the required readiness to provide guaranteed capacity.
  • We would like to inform you that from September 2 to September 3, 2020, at the request of the capacity source, the 9th power unit passed test for its readiness to provide guaranteed capacity, which was successful. The order to commission the 9th power unit was issued on September 2 at 14:51, the power unit was synchronized, kept the minimum guaranteed capacity set by the government (180 MW) and maintained it within the timeframes stipulated by the current legislation. Afterwards, at 15:49, the unit was stopped in reserve by the order of the Dispatcher.
  • We would like to inform you that from August 31 to September 1, 2020, at the request of the capacity source, the Gardabani TPP passed tests for readiness to provide guaranteed capacity, which were successful. The order to commission the Gardabani TPP was issued at 08:00 on August 31. The TPP was synchronized, kept the minimum guaranteed capacity set by the government (162 MW) and maintained within the timeframes stipulated by the current legislation. Testing of Gardabani Thermal Power Plant ended on September 1 at 15:23, after which, according to the Dispatcher's order, it remained in operation due to the system mode.
  • We would like to inform you that the Ltd "Gardabani Thermal Plant" completed the planned repair works at 00:00on August 31 instead 24:00 of September 4 and submitted the corrected statement on delivery of guaranteed capacity for September. Therefore, in September 2020, the Ltd "Gardabani Thermal Plant" has the necessary readiness (30 days) for the delivery of guaranteed capacity.

NEXT MONTH READINESS DAYS (FORECAST) OF GUARANTEED CAPACITY SOURCES