13/12/2019

In November 2019, the quantity of balancing electricity, purchased (sold) through ESCO was 288 854 817.6 kWh, which represents 27% of total delivery to the grid in mentioned month. The cost of balancing electricity have made up GEL 44 630 005.5.

- The electricity sold through the direct contracts

- Balancing electricity

In November, the Weighted Average Price of balancing electricity per kWh made up 15.4506703 Tetri, while the price of balancing electricity of the deregulated hydro power plants was 10.614 Tetri.

12/12/2019

From December 06, 2019, the Electricity Market Operator has registered the “Aqua hydro” Ltd  (in the part of Khelra HPP) to take part in the wholesale trade as Power Plant - During The Test Run And/Or Complex Testing, in accordance with the “Electricity (Capacity) Market Rules”.

12/12/2019

From December 06, 2019, the Electricity Market Operator has registered the “Aqua hydro” Ltd  (in the part of Ifari HPP) to take part in the wholesale trade as Power Plant - During The Test Run And/Or Complex Testing, in accordance with the “Electricity (Capacity) Market Rules”.

11/12/2019

From December 10, 2019, the Electricity Market Operator has registered the “NF Group” Ltd to take part in the wholesale trade as importer, in accordance with the “Electricity (Capacity) Market Rules”.

09/12/2019

Zaza Dvalishvili, CEO of the Electricity Market Operator (ESCO), made a presentation at the meeting held at the Ministry of Economy and Sustainable Development.

06/12/2019

From December 05, 2019, the Electricity Market Operator has registered the “Gardabani Thermal Power Plant 2” LTD (in the part of Gardabani Thermal Power Plant 2) to take part in the wholesale trade as Power Plant - During The Test Run And/Or Complex Testing, in accordance with the “Electricity (Capacity) Market Rules”.

06/12/2019

From December 04, 2019, the registration of “Gardabani Thermal Power Plant 2” LTD as Direct Customer is cancelled by the Electricity Market Operator and in accordance with the “Electricity (Capacity) Market Rules”, it is no more considered as a wholesale trade participant.

04/12/2019

For the purchase of one laptop and one printer, on December 03, 2019, ESCO announced NAT190023205 electronic tender with a total estimated cost of GEL 3 288.0. The deadline for submission of bids ends on December 11, 2019 at 14:30.

04/12/2019

A delegation of representatives from the energy sector of Nepal visited ESCO. The Electricity Market Operator acquainted the guests with the structure of the Georgian electricity market and the ongoing reform process, as a result of which the country's electricity sector will be significantly developed and its competitiveness in the region will be increased...

 

03/12/2019

From November 28, 2019, the Electricity Market Operator has registered the “AAD” LTD (in the part of Chapala HPP) to take part in the wholesale trade as Power Plant - During The Test Run And/Or Complex Testing, in accordance with the “Electricity (Capacity) Market Rules”.